Alberta data centre media monitoring
Every major data centre project in the province, tracked in one place.
reVerb follows data centre development across Alberta and pulls the headlines and application updates into a single feed. It is free to use, built for municipalities, counties, proponents and residents watching a project land in their county. Alongside the feed, reVerb provides data centre community consultation in Alberta, for councils weighing an application and for proponents bringing one forward. Stakeholder engagement on complex industrial projects is at the heart of our work.
Coverage by Project
Alberta data centre projects
Select any project for its details and every story we have logged on it, newest first. Every project also appears on the map below.
Southern Chestermere
- Budget
- $4 billion (proponent estimate)
- Timeline
- Land use approved April 2025; no construction date announced
Status: Proposed
Beacon AI Centers proposed a 400 MW AI and high-performance computing campus on about 310 acres in southern Chestermere. City council approved the land use change in April 2025.
No development permit or power plant application has been made public since, and Beacon's own campus list no longer includes this site.
In the News: Beacon Chestermere AI Data Centre
- Data Centre Wave Reaches Chestermere Region The Chestermere Anchor August 19, 2025
- Details emerge around Beacon AI's planned 400MW Alberta data center campuses DatacenterDynamics March 18, 2025
- Chestermere residents invited to learn about $4 billion proposed data centre StrathmoreNow March 16, 2025
- Beacon Data Centre Proposal Promises Economic Transformation in Chestermere The Chestermere Anchor March 3, 2025
- Over 300 permanent jobs promised for proposed AI data centre in Chestermere StrathmoreNow February 27, 2025
Wabamun area, Parkland County (exact site not published)
- Budget
- Not disclosed
- Timeline
- Not announced
Status: Proposed
Beacon AI Centers proposed a 400 MW AI data centre with on-site generation in Parkland County, in the Wabamun area between Keephills and Duffield. Parkland County noted the proposal in March 2026.
No rezoning, development permit or power plant application has been made public, and the exact site has not been published. The map pin shows the general area.
In the News: Beacon Harry Smith AI Data Centre
- Concerns raised over proposed AI data centre in Parkland County Global News 10/14/2026
- Two data processing facilities proposed in Parkland County Big West Country 92.9 March 10, 2026
- Canada's Beacon AI Centers appoints Josh Schertzer as CEO as company targets 4.9GW roll-out DatacenterDynamics May 16, 2025
- Details emerge around Beacon AI's planned 400MW Alberta data center campuses DatacenterDynamics March 18, 2025
Sturgeon County, about 7 km east of Gibbons
- Budget
- Not disclosed
- Timeline
- First operations targeted for fall 2027; AUC decision expected fall 2026
Status: In approvals
Beacon AI Centers plans an 800 MW AI campus on 320 acres in Alberta's Industrial Heartland, powered by a 920 MW on-site natural gas plant. Sturgeon County has issued a master site development permit.
The AUC reviewed the power plant through a written hearing that closed in July 2026, and its decision is pending.
In the News: Beacon Heartland AI Data Centre
- Finally Affected: AI data centre in Edmonton? No, three! The Friday Update 10/16/2026
- Sturgeon County leverages industrial zone for data centres Taproot Edmonton December 11, 2025
- Canada's Beacon AI Centers appoints Josh Schertzer as CEO as company targets 4.9GW roll-out DatacenterDynamics May 16, 2025
Near Indus, Rocky View County
- Budget
- Not disclosed (the earlier 400 MW design was $4 billion)
- Timeline
- Operations targeted for 2028 (energization was first targeted for December 2026)
Status: In approvals
Beacon AI Centers plans a 1,200 MW AI campus on 627 acres about 2 km northwest of Indus, powered by a 1,494 MW on-site natural gas plant. Rocky View County approved the area structure plan and zoning in June 2025 and later joined the AUC review as a participant.
The AUC held an oral hearing on the power plant in August 2026 and has not yet issued a decision.
In the News: Beacon Indus Data Centre Hub
- Parkland County community invited to open house on proposed data processing facility Big Country West 10/5/2026
- Public hearings begin for data centre near Indus CTV News Calgary August 18, 2026
- Councillors in rural county bordering Calgary vote to pause data centres The Canadian Press July 28, 2026
- Councillors in Rocky View County, bordering Calgary vote to pause data centres Global News July 28, 2026
- Alberta's AI data centre dreams run into global shortage of gas turbines The Narwhal July 9, 2026
- Opposition Mounts as Federal Agency Clears Early Hurdle for Proposed Indus Data Centre Power Plant The Chestermere Anchor April 7, 2026
- Rocky View County formally joins AUC review of Beacon AI Hub power plant DiscoverAirdrie February 17, 2026
- Canada's Beacon AI Centers appoints Josh Schertzer as CEO as company targets 4.9GW roll-out DatacenterDynamics May 16, 2025
- Details emerge around Beacon AI's planned 400MW Alberta data center campuses DatacenterDynamics March 18, 2025
- Nadia Partners launches Beacon AI Centers DatacenterDynamics January 20, 2025
- New company plans data center campuses totaling 1.2GW in Alberta, Canada DatacenterDynamics December 4, 2024
Near Saunders Lake, Leduc County
- Budget
- Not disclosed
- Timeline
- Not announced
Status: Proposed
Beacon AI Centers proposed a 400 MW AI data centre with on-site generation near Saunders Lake in Leduc County, close to Edmonton International Airport.
No Leduc County decision or power plant application has been made public, and Beacon's own campus list no longer includes this site.
In the News: Beacon Saunders Lake AI Data Centre
- Two data processing facilities proposed in Parkland County Big West Country 92.9 March 10, 2026
- Canada's Beacon AI Centers appoints Josh Schertzer as CEO as company targets 4.9GW roll-out DatacenterDynamics May 16, 2025
- Details emerge around Beacon AI's planned 400MW Alberta data center campuses DatacenterDynamics March 18, 2025
Blindman Industrial Park, Red Deer County
- Budget
- Not disclosed
- Timeline
- First data halls targeted for 2027 (completion was set for 2026)
Status: Under construction
Havenz Smart Communities, through Agritech Haven International, is building an AI and high-performance computing data centre in Blindman Industrial Park north of Red Deer.
Red Deer County approved the development permit in October 2025, and the AUC approved a 5 MW natural gas heat and power plant in September 2025. Construction is underway, and the company now describes a 10 MW first phase with room to grow.
In the News: Blindman Industrial Park Data Centre
- Alberta NDP gather feedback on AI data centres from central Albertans during town hall rdnewsNOW August 13, 2026
- Construction underway on data centre near Red Deer CTV News Edmonton February 5, 2026
- Construction accelerates at AI data centre near Red Deer rdnewsNOW January 26, 2026
- Alberta's new tech mandate set to come to life as Red Deer County approves data centre CBC News October 25, 2025
- Data center to be built on 120 acre land parcel between Calgary and Edmonton, Canada DatacenterDynamics October 9, 2025
- Red Deer County approves data centre Red Deer Advocate October 7, 2025
Alsike and Myers sites (exact sites not published)
- Budget
- About $1 billion per power plant (Kalina estimate)
- Timeline
- First investment decision targeted for 2027; no construction date
Status: Proposed
Kalina Distributed Power announced plans in February 2025 to build natural gas power plants with carbon capture for Crusoe AI data centres at three Alberta sites.
The Rocky View County site near Crossfield was withdrawn in April 2026 after local opposition. The Alsike and Myers sites remain proposed with no AUC or municipal application made public, and recent Kalina updates do not mention Crusoe. The map pin shows the Alsike area.
In the News: Crusoe and Kalina AI Data Centres
- Proposed data center outside Calgary, Canada, withdrawn by developer DatacenterDynamics June 30, 2026
- Alberta's AI data centre boom unleashes 'gold rush' for electricity allotments CBC News February 17, 2026
- Four AI data centre projects are in the works between Calgary and Edmonton Daily Hive November 13, 2025
- KALiNA targets Alberta data centres with CCGT+CCS Modern Power Systems June 24, 2025
- Crusoe, Kalina partner to develop natural gas powered AI data centers in Alberta, Canada DatacenterDynamics February 5, 2025
Southeast of Clive, Lacombe County
- Budget
- $2 million (proponent estimate)
- Timeline
- Construction tentatively March 2027 (operation was first targeted for October 2026)
Status: In approvals
Armada Nowlit Energy proposes a modular data processing facility with 19.8 MW of on-site natural gas generation on about 4.4 acres southeast of Clive. The power is for use on site only, with no export to the grid.
Lacombe County is reviewing an application to redesignate the land from agricultural to heavy industrial, and no approvals have been granted.
In the News: Clive Data Centre
- Information session scheduled for proposed Clive 8-16 facility One FM September 29, 2026
- Public meeting set for proposed Clive data centre CentralAlbertaOnline September 28, 2026
- What Lacombe County wants residents to know about data centres CentralAlbertaOnline September 2, 2026
- Lacombe County Council reviews plans for projects across the region CentralAlbertaOnline September 1, 2026
- Proposed Clive data centre under municipal review CentralAlbertaOnline August 27, 2026
- Data Centre facility under review in Lacombe County Lacombe Express August 27, 2026
- Sept. 30 public open house set for Clive data centre Red Deer Advocate August 26, 2026
- Lacombe County listens to presentations on fluoride survey, proposed data centre CentralAlbertaOnline March 17, 2026
- Power facility and data centre proposed near Clive Red Deer Advocate March 12, 2026
Sturgeon County, about 8.5 km east of Gibbons
- Budget
- More than $13 billion (Meta)
- Timeline
- Ground broken July 2026; construction to 2029; dedicated gas power in service second half of 2030
Status: Under construction
Meta is building its first Canadian data centre, a 1 GW AI campus in Alberta's Industrial Heartland about 30 km north of Edmonton. Sturgeon County issued the development permit in June 2026 and Meta broke ground on July 8, 2026.
Power will come from the Greenlight Electricity Centre, a 1,864 MW natural gas plant the AUC approved in June 2026, with Capital Power supplying 250 MW in the meantime.
In the News: Meta Data Centre Sturgeon County
- Will Meta's data centre raise Alberta power bills? Experts say it could CBC News September 28, 2026
- Construction moving ahead with Meta's data centre in Sturgeon County CTV News Edmonton September 17, 2026
- Data centre construction transforms Sturgeon County land CTV News Edmonton September 17, 2026
- Sturgeon County lays out rules for data centres as Meta project moves ahead St. Albert Gazette September 2, 2026
- Meta lays out AI data centre plan to Sturgeon County council St. Albert Gazette July 20, 2026
- Alberta premier offers reassurances on massive Meta data centre CBC News July 11, 2026
- Residents sound off on Meta data centre in Sturgeon County St. Albert Gazette July 10, 2026
- Meta plans $9.17bn gigawatt-scale data center in Alberta, Canada DatacenterDynamics July 9, 2026
- Meta building its first Canadian data centre northeast of Edmonton CBC News July 8, 2026
- Meta to build $13 billion data centre in Alberta, largest outside the U.S. Global News July 8, 2026
- Meta to build $13B data centre north of Edmonton, its first in Canada Calgary Journal July 8, 2026
- Meta announced as company behind $13 billion Sturgeon County AI data centre Heartland News July 8, 2026
Former Carmon Creek site, Northern Sunrise County
- Budget
- Not disclosed
- Timeline
- First power targeted for 2027
Status: In approvals
Mihta Askiy Datacenter LP, majority owned by Woodland Cree First Nation with Sovereign Digital Infrastructure, plans a 650 MW AI data centre at the former Shell Carmon Creek site about 40 km northeast of Peace River.
Federal and provincial regulators decided in spring 2026 that no further impact assessment is required. Power plant and municipal approvals are still to come.
In the News: Mihta Askiy Data Centre
- Proposed northern Alberta AI data centre raises concerns over power demand and water use Edmonton Journal July 6, 2026
- Alberta, Feds Waive Further Impact Assessments on Mihta Askiy Data Centre Project Connect CRE April 28, 2026
- Impact assessments not required for Olds, Mihta Askiy data centres. Expert says legislation needs to catch up CBC News April 26, 2026
- Woodland Cree First Nation to develop 650MW data center in Alberta, Canada DatacenterDynamics July 16, 2025
- Indigenous-Led Data Centre Planned for Alberta Power Plant Data Centre Magazine July 16, 2025
- Indigenous-led data centre in Alberta slated for development amid AI infrastructure boom CBC News July 16, 2025
- Woodland Cree announces major indigenous-led data center project in Northern Alberta Western Standard July 15, 2025
Strathmore
- Budget
- Not disclosed
- Timeline
- Operations were targeted for June 2026; not yet confirmed
Status: Proposed
Prairie Sky Data Solutions plans to convert a former cannabis facility in Strathmore into an AI data centre, starting with 1.5 MW of power and growing to 13 MW by the end of the first phase.
The company announced the project in August 2025 and targeted operations for June 2026. No public update on construction or operations has been reported since.
In the News: Prairie Sky Data Solutions Data Centre Strathmore
- Data Centre Wave Reaches Chestermere Region The Chestermere Anchor August 19, 2025
- Strathmore celebrates plans to bring in AI data centre StrathmoreNow August 7, 2025
- Prairie Sky Data Solutions prepares to launch local AI data center Strathmore Times August 6, 2025
Olds, Mountain View County
- Budget
- $10 billion (proponent estimate)
- Timeline
- Construction was planned for March 2026; power plant refused August 2026
Status: Refused
Synapse Data Center proposed a 1 GW AI data centre in the northeast industrial area of Olds, powered by a 1,400 MW natural gas plant with 1,800 MW of backup diesel generation.
The Alberta Utilities Commission (AUC) closed the first power plant application in March 2026 and refused the second in August 2026 (Decision 30732-D01-2026), finding the site not suitable. About 1,500 parties asked to take part in that proceeding and more than 900 were granted standing. Synapse has said the Olds project will not proceed as proposed.
In the News: Synapse Olds Data Centre
- Proponent of failed Olds data centre still keen on Alberta prospects Olds Albertan August 18, 2026
- Alberta Utilities Commission rejects power plant for Olds data centre plan CBC News August 17, 2026
- Olds data centre location rejected by Alberta regulator Red Deer Advocate August 17, 2026
- Hundreds want a say in Synapse data centre project Red Deer Advocate August 6, 2026
- When big data comes to a small town: The project riling up citizens in Olds, Alta. CBC News July 6, 2026
- Olds power plant, data centre application paused as Alberta regulator seeks answers CBC News June 17, 2026
- Town of Olds conditionally supports Synapse's proposed $10 billion AI data centre Olds Albertan June 2, 2026
- Data centre proposal in Olds 'consuming' the lives of some living next door CBC News May 4, 2026
- AI data centre, power plant proposal in Olds, Alta., back on the table CBC News April 10, 2026
- Alberta regulator nixes power plant proposal for Canada's largest AI data centre complex CBC News March 6, 2026
- A $10-billion AI data centre races ahead in a rural Alberta town, population 9,679 The Narwhal February 23, 2026
- Olds chosen as home to Canada's largest data centre Olds Albertan January 27, 2026
Greenview Industrial Gateway, MD of Greenview
- Budget
- $70 billion at full build-out (proponent estimate)
- Timeline
- Construction 2027 if approved, phased development from 2029 (first phase was targeted for 2027)
Status: Proposed
O'Leary Digital proposes an AI data centre park with up to 9 GW of on-site generation on the Greenview Industrial Gateway, about 40 km south of Grande Prairie. The first phase has grown to 2 GW from the 1.4 GW announced in December 2024.
The MD of Greenview holds the Smoky River water licence for the site, and Sturgeon Lake Cree Nation's judicial review of that licence goes to court in December 2026. The province designated the gateway an industrial zone in August 2026.
In the News: Wonder Valley AI Data Centre Park
- O'Leary Digital appeal adds new front to Sturgeon Lake Cree Nation's water license challenge Windspeaker , via Turtle Island News September 11, 2026
- Site of proposed Wonder Valley data centre in northern Alberta gets special industrial zone designation CBC News September 3, 2026
- Sturgeon Lake Cree Nation in Alberta claims victory in first battle against 'mind-boggling, massive' AI data centre APTN News August 14, 2026
- O'Leary hits roadblock, as AI company dropped from lawsuit Canada's National Observer August 14, 2026
- First Nation in court to challenge proposed Wonder Valley AI data centre project in northern Alberta CBC News June 10, 2026
- Northern Albertans raise concerns about Wonder Valley AI data centre at packed community hall CBC News June 5, 2026
- Updated info about water use, timelines for proposed Wonder Valley AI project in Alberta CBC News June 3, 2026
- First Nation's appeal on Wonder Valley water dismissed Town & Country News May 14, 2026
- Wonder Valley AI Data Centre exempt from provincial environmental impact assessment, still needs permits CBC News April 10, 2026
- The truth about Wonder Valley, Kevin O'Leary's data-centre dream The Logic December 10, 2025
- Why celebrity investor Kevin O'Leary is proposing a massive AI data centre in northern Alberta CBC News December 11, 2024
Olds, Mountain View County (site not public)
- Budget
- $200 million to $300 million to start (Town of Olds)
- Timeline
- Operations were expected in late 2026; no development permit filed yet
Status: Proposed
Data District, a division of Swiss asset manager Alcral AG, announced four Alberta data centres in December 2025 with Technologies New Energy as its power and supply chain partner. The four sites total about 240 MW and $1.26 billion.
Data District has bought land in Olds, and as of March 2026 the Town had received no development permit or other application. This project is separate from the Synapse proposal in Olds.
In the News: Data District Data Centre Olds
- Olds awaiting formal applications for proposed data centre Central Alberta Online February 18, 2026
- While data centre announced for Olds, no application yet Olds Albertan January 23, 2026
- Swiss-Backed Data Center Plan Targets €8 Billion in Gas-Rich Alberta Bloomberg January 2, 2026
- Olds selected for data centre project, jobs expected by 2026 Discover Airdrie December 30, 2025
- Swiss-Backed Firm Announces $1.3B Data Center Development in Alberta The Deep Dive December 21, 2025
- Data centre announced for Olds Red Deer Advocate December 18, 2025
- Town of Olds welcomes Data District Inc. with major data centre investment rdnewsNOW December 18, 2025
- TNE partners with Data District to support 1GW data center pipeline in Alberta, Canada DatacenterDynamics December 18, 2025
- TNE, Data District to Develop Four New Data Centres in Alberta Connect CRE Canada December 18, 2025
- Data centre planned for Olds set to create 200 indirect jobs, 70 permanent ones Olds Albertan December 18, 2025
- European partners give green light to four new data centres in Alberta Edmonton Journal December 17, 2025
MD of Bonnyville (site not finalized)
- Budget
- Not disclosed ($1.26 billion across all four sites)
- Timeline
- Construction planned for 2027
Status: Proposed
Data District, a division of Swiss asset manager Alcral AG, announced four Alberta data centres in December 2025 with Technologies New Energy as its power and supply chain partner. The four sites total about 240 MW and $1.26 billion.
The Bonnyville-area site is in the MD of Bonnyville, with construction planned for 2027. The exact site had not been finalized as of January 2026.
In the News: Data District Data Centre Bonnyville
- Major AI Data Centre Project Eyed for Bonnyville Area as Part of $1.26B Alberta Investment Lakeland Connect January 12, 2026
- Swiss-Backed Data Center Plan Targets €8 Billion in Gas-Rich Alberta Bloomberg January 2, 2026
- Swiss-Backed Firm Announces $1.3B Data Center Development in Alberta The Deep Dive December 21, 2025
- TNE partners with Data District to support 1GW data center pipeline in Alberta, Canada DatacenterDynamics December 18, 2025
- TNE, Data District to Develop Four New Data Centres in Alberta Connect CRE Canada December 18, 2025
- European partners give green light to four new data centres in Alberta Edmonton Journal December 17, 2025
Calgary area (site not public)
- Budget
- Not disclosed ($1.26 billion across all four sites)
- Timeline
- Not announced
Status: Proposed
Data District, a division of Swiss asset manager Alcral AG, announced four Alberta data centres in December 2025 with Technologies New Energy as its power and supply chain partner. The four sites total about 240 MW and $1.26 billion.
No Calgary-area site, filing or date has been made public. The map pin shows the general area.
In the News: Data District Data Centre Calgary
- Swiss-Backed Data Center Plan Targets €8 Billion in Gas-Rich Alberta Bloomberg January 2, 2026
- Swiss-Backed Firm Announces $1.3B Data Center Development in Alberta The Deep Dive December 21, 2025
- TNE partners with Data District to support 1GW data center pipeline in Alberta, Canada DatacenterDynamics December 18, 2025
- TNE, Data District to Develop Four New Data Centres in Alberta Connect CRE Canada December 18, 2025
- European partners give green light to four new data centres in Alberta Edmonton Journal December 17, 2025
Edmonton area (site not public)
- Budget
- Not disclosed ($1.26 billion across all four sites)
- Timeline
- Not announced
Status: Proposed
Data District, a division of Swiss asset manager Alcral AG, announced four Alberta data centres in December 2025 with Technologies New Energy as its power and supply chain partner. The four sites total about 240 MW and $1.26 billion.
No Edmonton-area site, filing or date has been made public. The map pin shows the general area.
In the News: Data District Data Centre Edmonton
- Swiss-Backed Data Center Plan Targets €8 Billion in Gas-Rich Alberta Bloomberg January 2, 2026
- Swiss-Backed Firm Announces $1.3B Data Center Development in Alberta The Deep Dive December 21, 2025
- TNE partners with Data District to support 1GW data center pipeline in Alberta, Canada DatacenterDynamics December 18, 2025
- TNE, Data District to Develop Four New Data Centres in Alberta Connect CRE Canada December 18, 2025
- European partners give green light to four new data centres in Alberta Edmonton Journal December 17, 2025
Sexsmith, Alberta
Status: Proposed
In the News: Sexsmith Data Centre
Red Deer County, Alberta
Status: Proposed
In the News: Red Deer County Data Centre
- Public hearing set for Red Deer County data centre The Advocate 10/6/2026
- $300 million AI research lab, data centre proposed east of Penhold The Albertan 9/30/2026
Edmonton, Alberta
Status: Proposed
Proposed location in Edmonton Energy and Technology Park
In the News: Northeast Edmonton Data Centre
- Edmonton invites input on data centre development Heartland News 10/15/2026
- Major data centre campus proposed for northeast Edmonton Daily Hive 10/6/2026
- Data Centre campus proposed in North East Edmonton Taproot Edmonton 9/30/2026
Travers Reservoir
Status: Proposed
Planned as a hyperscale AI data centre with a target IT load of up to 2,000 MW (2.4 gigawatts in some news reports), potentially built over four 500 MW phases, featuring multiple data centre buildings.
The project is currently under review following a judicial challenge from local residents. Settlements regarding rezoning and environmental approvals remain pending through the Alberta Court of King’s Bench
In the News: Travers AI Data Centre Campus
- Residents group opposed to proposed AI data centre granted special hearing next year Lethbridge News Now 10/7/2026
Yellowhead County
- Budget
- 20 billion
- Timeline
- Completed 2030
Status: Proposed
Emerald Energy Technologies, a wholly-owned subsidiary of Tourmaline Oil Corp, is planning to build a power-generation facility and a data centre called Malachite One. The proposed site is on Crown land, adjacent to Tourmaline’s active Banshee Gas Plant about 40 kilometres southwest of Edson in Yellowhead County. The project would convert 150 million cubic feet of natural gas daily into one gigawatt of electricity to power the data centre.
Project Map
Select a dot to preview a project. Where dots overlap, you get a list of every project at that spot.
SUBSCRIBE
Want updates as soon as new projects, delays or funding announcements are posted?
Sign up below to receive email notifications when we update this page.
Whether you're a contractor, planner or public sector staff, we’ll help you stay on top of data centre projects across Alberta.
Disclaimer:
This page is for informational purposes only and reflects publicly available data from news sources, government releases, and project websites. reVerb Communications does not guarantee the accuracy, completeness, or timeliness of the information provided. This is a free service intended to support awareness and public engagement. For official project details, please refer directly to the relevant project owner or agency.
Recommended Read: What is Media Monitoring?
Go to the source
Provincial
- AI Data Centres in Alberta The province's public information site on power, water, environment and community questions.
- AI Data Centres Strategy The strategy behind the province's approach, with the full document and fact sheet.
- By the numbers The province's key figures, each one defined, sourced and dated.
- Approvals and permits Which body approves what, from AUC power plant permits to municipal development permits.
Grid and regulator
- AESO large load projects Connection allocations, the Phase 2 framework and the data centre connection guide.
- Map of data centre projects The AESO's live map of data centre projects moving through the connection process.
- Connection project list The monthly project-level file showing status, planning area and staged energization.
- How an AUC application is reviewed The nine steps under Rule 007, from participant involvement through to appeal.
Links go to primary sources. reVerb has no affiliation with these bodies and takes no position on the projects before them.